The site of our energy optimization project has been cleared of old equipment ready to have our new kit installed.


Back in June we headed down to Northamptonshire to begin the clearout for our big energy recovery project. It took a 50-ton crane to remove the old de-commissioned spiral and plate heat exchangers, but now the floor is ready to be concreted and prepared for the installation of the four new plate heat exchangers.

spiral heat exchanger lifted by crane Above: the last spiral heat exchanger being lifted away.
plate heat exchanger lifted by crane Above: the last plate heat exchanger being lifted away.

It doesn't look like much right now, but with all of our new kit in place down the line, this will be a hugely worthwhile investment!

vacated area Above: area with all of the de-commissioned equipment removed.